Loading...
Solid Waste Sites UpdateSolid Waste Convenience Sites Construction Updates July 19, 2022 Level Run Site 7550 Level Run Road, Long Island Construction Contract: $375,694 Level Run –Entrance Into Site Level Run Showing compactor pad in middle of site. Compactor installation scheduled for 7/28 Level Run Showing compactor pad in middle of site. Recycling and bulk debris container pads beyond. Climax Site 8004 Climax Road, Gretna Compactor installation scheduled for 7/26 Construction Contract: $513,879 Climax Site Attendant control building in the foreground Recycling container pads beyond Climax Site Walls and pads for bulk debris containers Meadow Ridge Ct. Site 211 Meadow Ridge Court, Gretna, VA Grading began in early June Completion is expected in early Spring of 2023 Current Sites In The Design Phase For Improvements 1.Mount Hermon (3575 Franklin Turnpike, Danville) 2.Berry Hill (110 Target Drive, Danville) 3.Motley (1130 Highwayview Road, Hurt) Mount Hermon Draft Expansion -Adds space for two new compactors and two recycling or roll-off boxes. -Budget construction estimate is expected next week. Motley Site *Currently awaiting completion of survey Considerations for revised site: 1.Better Incorporation of Recycling Containers 2.Improved Traffic Flow / Increased Capacity 3.Improving Existing Retaining Walls 4.Enhancing Access to Site Facilities 5.Facilitate Increased Use of Compactors (vs. Open-tops) for disposal of household waste. Berry Hill Site *Currently awaiting completion of survey Considerations for revised site: 1.Better incorporation of waste & recycling containers 2.Improved traffic flow and capacity, including expansion of the paved area in the portion shown above outlined in red. 3.Enhancing safety aspects of site facilities. 4.Facilitate increased use of compactor for household waste disposal in order to increase collections efficiency. Berry Hill Site