Solid Waste Sites UpdateSolid Waste Convenience Sites
Construction Updates
July 19, 2022
Level Run Site
7550 Level Run Road, Long Island
Construction Contract: $375,694
Level Run –Entrance Into Site
Level Run
Showing compactor pad in middle of site.
Compactor installation scheduled for 7/28
Level Run
Showing compactor pad in middle of site.
Recycling and bulk debris container pads beyond.
Climax Site
8004 Climax Road, Gretna
Compactor installation scheduled for 7/26
Construction Contract: $513,879
Climax Site
Attendant control building in the foreground
Recycling container pads beyond
Climax Site
Walls and pads for bulk debris containers
Meadow Ridge Ct. Site
211 Meadow Ridge Court, Gretna, VA
Grading began in early June
Completion is expected in early Spring of 2023
Current Sites In The Design Phase For Improvements
1.Mount Hermon (3575 Franklin Turnpike, Danville)
2.Berry Hill (110 Target Drive, Danville)
3.Motley (1130 Highwayview Road, Hurt)
Mount Hermon
Draft Expansion
-Adds space for two new
compactors and two
recycling or roll-off boxes.
-Budget construction
estimate is expected next
week.
Motley Site
*Currently awaiting completion of survey
Considerations for revised site:
1.Better Incorporation of Recycling Containers
2.Improved Traffic Flow / Increased Capacity
3.Improving Existing Retaining Walls
4.Enhancing Access to Site Facilities
5.Facilitate Increased Use of Compactors (vs. Open-tops)
for disposal of household waste.
Berry Hill Site
*Currently awaiting completion
of survey
Considerations for revised site:
1.Better incorporation of waste & recycling containers
2.Improved traffic flow and capacity, including expansion of the paved
area in the portion shown above outlined in red.
3.Enhancing safety aspects of site facilities.
4.Facilitate increased use of compactor for household waste disposal in
order to increase collections efficiency.
Berry Hill Site