RiverStreet - Pittsylvania County BOS Update August 2024ROB TAYLOR -DIRECTOR OF BUSINESS DEVELOPMENT &
GOVERNMENT AFFAIRS
PITTSYLVANIA COUNTY FTTH UPDATE
AUGUST 20, 2024
PITTSYLVANIA COUNTY –CAF II & VATI APPLICATION LOCATIONS
CAF AWARD
PROJECT AREA
RDOF & VATI 22
LOCATIONS
CAF II & VATI
APPLICATION
LOCATIONS PASSED
BY RSN FTTH PLAN
RSN RDOF –8,369
UNFUNDED –3,616
VATI 2022 TOTAL -
11,985
VATI 2023 TOTAL -
2,102
CAF II -2,412
GRAND TOTAL -
16,499
VATI 23 LOCATIONS
NEW FIBER
VATI 23 LOCATIONS
EXISTING FIBER
CURRENT SERVICE MAP
PITTSYLVANIA GENERAL INFORMATION
●As of Wednesday, 08/14/2024 we had 760 customers installed which is an increase of 148 locations since our last reporting in June 2024○Currently have 309 orders in process
●Since our last report the number of locations passed has increased from 3,790 locations to 4,798 or 1,008○With 1,069 locations installed or in process, the current take rate is 22% which is 50% higher than the June reporting of 14%
●Strawberry cabinets 7, 8, and 10 through 13 are currently under construction
●Chestnut CO and cabinets 1 through 4 are currently under construction
●453 locations are currently in Pre-Order Status
●Since the last reporting, RSN Marketing team has had sign up events in Downtown Chatham, Java Fire Dept.(this was a Saturday event that was extremely well attended), County Community Center, Union Hall Elem School -Open House.
Pittsylvania County –Current Project Timeline
Tasks Up Next: August❑Begin Construction in Strawberry Cabinet 8
❑Complete Splicing and Testing -Strawberry Cabinets 4&5❑Complete Construction -Strawberry Cabinet 9
❑Begin Splicing -Strawberry Cabinet 9
❑Complete Brosville Staking -Construction to Begin Next Quarter
July Tasks Underway or Completed ✔Complete Construction -Strawberry Cabinets 7&9
✔Begin Splicing and Testing -Strawberry Cabinets 4&5✔Begin Staking -Brightsville CO and Cabinet 3
✔Begin Construction -Chestnut CO and Cabinets 1-4