JailPITTSYLVANIA COUNTY
COMMUNITY BASED CORRECTIONS PLAN
NEEDS ASSESSMENT AND
PLANNING STUDY UPDATE
December 19, 2023
VOTECH
Local and Regional jails of Virginia and the Carolinas
Local and Regional jails of Virginia and the Carolinas
Aerial RSW Regional Jail
Exterior RSW Regional Jail
Aerial BR Regional Jail – Amherst
Image provided by Google
Exterior image BR Regional Jail
Exterior front ‘bird’s eye’ view
Exterior rear ‘bird’s eye’ view
Exterior front arrival view (in progress design)
Exterior front arrival view (in progress design)
SCHEDULE – 2024-2025
Prepare/Submit CBCP Needs Assessment and Planning Study December 31, 2023
BOS meetings about project and approval of project January - April, 2024
Resolution from BOS March, 2024
Resolution to BOLRJ April, 2024
BOLRJ Approval CBCP Needs Assessment May, 2024
BOLRJ Approval of CBCP Planning Study July-August, 2024
Application to Treasury Board for bonds for reimbursement June, 2024
DOC submits to Department of Planning and Budget/DEB Sept-Oct, 2024
Receive Governor approval for funding and inclusion in the budget bill December 1, 2024
Receive Legislative approval (Legislative session) June, 2025
Project Planning, Design, and Construction Schedule
Negotiate A/E Contract with Moseley Architects December 2023 - June, 2025
Receive Legislative approval (Legislative session) June, 2025
County issues Design NTP (or earlier at risk) June, 2025
VDOC required Value Engineering on Design November, 2025
Complete Construction Documents/secure County design approvals March, 2026
Advertise for bids May, 2026
Receive Bids May, 2026
Negotiate Construction Contract August, 2026
Notice to Proceed (Construction) August, 2026
Substantially Complete construction (14 months – to be confirmed) October, 2027
Final Completion of project November, 2027
SCHEDULE 2025-2027
BUDGET ESTIMATE
REFER TO
VADOC PART I FORMULA NOTES ON
FOLLOWING
Expansion of Existing Jail PAGE
MEANS COSTS (2023 Const Cost Data) 371.67 PER SF 371.67 PER SF 1
MARSHAL & SWIFT MULTIPLIER X 0.95 0.95 2
MEDIAN COST PER SQ FT =353.09 PER SF 353.09 PER SF
**413.82 PER SF 413.82 PER SF
PROPOSED SF X 98,122 SF 97,622 SF 3
MEDIAN CONSTRUCTION COST =$40,604,732 $40,397,823
**Escalation/Inflation Values as follows:
July 2023 to June 2024 4.95 %
FY 2025 4.5 %General Assembly Approval and funding June 2025
FY 2026 3.5 %Design June 2025 to June 2026
FY 2027 3.25 %June 2027 is the midpoint of construction
Cumulative Value 17.20 %4
MOSELEY OPINION
PLANNING STUDY PROJECT ESTIMATE LOCALITY VADOC
(EXCLUSIVE OF BONDS OR FINANCING)REQUESTED ELIGIBLE
COST COST
PART I - PROJECT CONSTRUCTION COSTS
BUILDING CONSTRUCTION COST 40,604,732 40,397,823
SITEWORK (15 acres @ $317,000/acre)4,755,000 4,755,000 5
PART I PROJECT CONSTRUCTION COSTS SUBTOTAL:45,359,732 45,152,823
PART II - PROJECT SPECIFIC COSTS
INCREASE CORE TO 202 BEDS - Programmed Square Footage
7,652 SF @ $COST INCLUDED ABOVE
WATER TOWER
295,000 GAL @ $3.39 $1,000,000 1,000,000 6
TURN LANE IMPROVEMENTS
$400,000 400,000 7
PUMP STATION IMPROVEMENTS
$50,000 50,000 8
ACCESS ROAD FROM ROUTE 29 TO SITE PROPER
680 LF @ $588.24 $400,000 400,000 9
ENCLOSED AND PARTIALLY COVERED OUTDOOR REC YARDS
8,632 LF @ $206.91 $1,786,042 1,786,042 9
PART II PROJECT SPECIFIC COSTS SUBTOTAL:$3,636,042 $3,636,042
ESCALATION / INFLATION
(July 2023 to midpoint of construction June 2027)
PITTSYLVANIA COUNTY NEW JAIL
COST ANALYSIS - SUMMARY
******************************************************
*******************************************************
PART III - OTHER PROJECT COSTS
A/E FEES (8% PART I)$3,628,779 3,628,779
A/E FEES (10% PART II)$363,604 363,604
CBCP / PLANNING STUDY $260,222 260,222 10
EARLY PLANNING COST OF SERVICES $83,000 83,000 11
SITE ACQUISITION (32 acres x $16,000/ acre)$500,000 500,000 12
SITE ACQUISITION FEES $15,967 15,967 13
VALUE ENGINEERING STUDY $50,000 50,000
FF&E ($30/SF) INCLUDING COST OF SERVICES $2,943,660 294,366
COMMUNICATIONS/DATA EQUIPMENT ($1/SF)$98,122 98,122
TEST BORINGS/TESTING/SPEC INSP (1% of Construction)$489,958 489,958
SURVEY, TOPO & UTILITY LOCATOR $90,000 90,000
PRINTING & REPRODUCTION $10,000 10,000
PERMITS, FEES & CONNECTION (1% of Construction)$489,958 489,958
PART III OTHER COSTS SUBTOTAL:$9,023,269 $6,373,975
CONTINGENCY (8% OF PART I AND PART II)$3,919,662 $3,903,109
TOTAL CONSTRUCTION COSTS:$61,938,705 $59,065,949
TOTAL PROJECT COST :$61,938,705 $59,065,949
Need to borrow
PER BED PROJECT COST @ 146 BEDS (with 202 CORE):$424,238 $404,561
25% of $15,484,676 $14,766,487
BUDGET ESTIMATE
MOSELEY OPINION
PLANNING STUDY PROJECT ESTIMATE LOCALITY VADOC
(EXCLUSIVE OF BONDS OR FINANCING)REQUESTED ELIGIBLE
COST COST