VDOT - Route 29 Tightsqueeze Improvements - Cancellation, Options, and Next StepaDOT riia Department of Transportation ■ ROUTE 29 TIGHTSQUEEZE IMPROVEMENTS - CANCELATION, OPTIONS AND NEXT STEPS Chris Winstead, P.E. July 18, 2023 0 We cannot move the SMART SCALE funds from Tightsqueeze to another project (example: cannot be used to repair/replace the bridge on Route 57 over the Banister River) • Code of Virginia (Section 33.2-358) defines SMART SCALE and State of Good Repair funding VDOT I Virginia Department of Transportation 2 Code of Virginia Section 33.2-214 dictates only the Commonwealth Transportation Board can cancel SMART SCALE funded projects. CTB likely to receive the project cancellation presentation at either the September or October meeting with possible CTB action the following month. VD13T Virginia Department of Transportation 3 R-Cut -Route 29 at Route 703 (Tightsqueeze Road) UPC 119165 • Submitted by Pittsylvania County in Round 4 of SMART SCALE • Total Original Project Cost: $11,423,966 • Total SMART SCALE Request: $11,423,966 • Request funded with District Grant Program funds • Original Scope: • Reconfigure the intersection at US 29 and Tightsqueeze Road to a Restricted Crossing U-Turn (R-CUT) • Construct signalized median openings • Construct a left -in only median north of the intersection • Benefits were primarily due to safety VDE3T Virginia Department of Transportation 4 %VDC3T I Virginia Department of Transportation What changed after project selection? • Due to significant public opposition to the project in response to the Public Hearing held in May 2023, Pittsylvania county requested to place the project on hold to determine next steps Short term actions to address safety: • Specific signal phasing plans will enable the existing signal to function more efficiently during peak hours, reducing rear end collisions • Transverse rumble strips in advance of the signal will also assist in reducing rear end collisions • Investigate possibility of providing overhead lighting at the intersection using existing utility poles. VDOT Virginia Department of Transportation 6 • Possibly approve proposed project cancellation in October 2023 • Transfer the District Grant Program to the Lynchburg District deallocation balance entry (UPC-21764) • Note the Code of Virginia Section 33.2-214 does state the locality requesting project termination "may be required to reimburse the Department for all funds expended on the project." \/DOT i Virginia Department of Transportation 7 • No RCUT but instead provide additional turn lane improvements on Tightsqueeze and Fairview Roads at the intersection with Route 29. • Benefits: • Increased capacity • Reduce crashes through access management • Traditional project that the public understands • Concerns: • Will involve right of way acquisition (including a possible total take) • Will restrict some turning movements due to a small raised median • Has not been fully scoped yet VDOT I Virginia Department of Transportation g Operational Improvements -Potential Alternative znda PM No Build trasuxxt�a `h'c�stbtx�+d - €v�d� sca; US 29 Tight Squeeze Tight Squeeze Rd Fairview Rd � e U5 29 :o- _L Lett, Tht h € fight Left naeujh' „ Right Left Thrtnagt � Right e Left n 95th %❑uam Lerwo IRY comhnl ❑&SY (a) Los LOS Y k mft4bon DMV(s Los Eamwnd 2045 PM Aft Build Squeeze Tight Squeeeze US 29 & Tight Squeeze Rd Left .ThrOtXP Right Rd f Fairview Rd Traffic Vokune(veMr) Man 95th %Oueuo Length (it) ®®- Con±rel Delay(s) LOS ttJ• - Approach Delay (a) LOS tritersectian Delay (S) .ViosiS`e�arsC-_-_ta�xtr=/x�ter�3, - Scxtutoc�zd Ftm ieca Rd , US US 29 Leta ' Thrvoiih Right l : Left ° Through Right R' LaCt ; Thts3tuth MOW i fi `i T t If interested now: • Send letter requesting VDOT develop an alternative scope to the RCUT within the requirements of SMART SCALE • VDOT conducts a Citizens Information Meeting within 60-90 days and receives public input. • VDOT then seeks a BOS resolution of support for the alternative scope and VDOT would proceed with project development, including another future Design Public Hearing. If not interested now: • VDOT proceeds with advancing your request to cancel the project to the CTB. The project funding returns to the District Grant Program for future rounds of SMARTSCALE. VDOT Virginia Department of Transportation 10 DOT iia Department of Transportation