RiverStreet PresentationROBERT TAYLOR –DIRECTOR OF BUSINESS DEVELOPMENT &
GOVERNMENT RELATIONS
PITTSYLVANIA COUNTY FTTH UPDATE –FEBRUARY 21, 2023
PITTSYLVANIA COUNTY
FTTH OVERVIEW
PITTSYLVANIA COUNTY –CAF II & VATI APPLICATION LOCATIONS
CAF AWARD
PROJECT AREA
RDOF AWARD
PROJECT AREA
CAFF II & VATI
APPLICATION
LOCATIONS PASSED
BY RSN FTTH PLAN
RSN RDOF –8,369
UNFUNDED –3,616
VATI TOTAL -
11,985
CAF II -2,412
GRAND TOTAL -
14,397
UNFUNDED
PROJECT AREA
PITTSYLVANIA COUNTY VATI 2022 APPLICATION
PITTSYLVANIA COUNTY CAF II
Federal Funds -CAF II $4,056,552 39.8%
Federal Funds -ARP $0 0.0%
State Funds -VATI $0 0.0%
Local Funds Phase $0 0.0%
RSN Matching Funds -Cash / Loan $6,125,940 60.2%
$10,182,492 100.0%
Federal Funds –RDOF I (years 1 -3)$2,301,619 3.0%
Local Funds –ARP $16,528,939 21.8%
State Funds -VATI $39,510,529 52.2%
RSN Matching Funds –RDOF 1 (years 4 –10)$5,370,445 7.1%
RSN Matching Funds –Installation (40% Take)$11,985,000 15.9%
$75,696,532 100.0%
PITTSYLVANIA COUNTY
FTTH UPDATE
Pittsylvania County Service Areas
•Pittsylvania Build Sequence
•Phase 1
•Renan
•Sandy Level
•Phase 2
•Strawberry
•Java
•Phase 3
•Brosville
•Ringgold
•Chestnut
•Phase 4
•Brightville
•Gretna
•Hurt
•Lakeside
Sandy Level & Renan Service Areas
Strawberry & Java Service Areas
Brosville, Ringgold, & Chestnut Service Areas
Lakeside, Gretna/Brightville & Hurt Service Areas
PITTSYLVANIA COUNTY -WORK IN PROCESS
PITTSYLVANIA COUNTY -WORK IN PROCESS
STATUS OF PITTSYLVANIA COUNTY FTTH
BROADBAND PROJECT
-Fiber design is 75% completed
-Property Acquisition is 100% completed
-Six sites are existing RSN sites
-5 sites have been procured
-Staking of County is 35% completed
-VDOT Land Use Permits (LUP)Right of Ways & Easements -30% completed
-Construction is currently underway in Sandy Level & Renan
-Sandy Level has 2 plow & 2 bore crews
-Renan has 2 plow & 2 bore crews
-10,958’ of fiber has been installed
-4,302’ of conduit has been bored
-12 peds have been installed
-1 vault has been
-Materials -Shipments arriving weekly
-100% of poles/stubs and handholds are available for both project
-100% of fiber on hand for Renan and 40% on hand for Sandy Level
-20% of pedestals on hand for Renan and 50% on hand for Sandy Level
-Marketing & County Administration working on a possible Groundbreaking at Java Vol. Fire
Department end of March or early April
QUESTIONS