Broadband BOS Presentation 1-17-2023Broadband Update 1/17/2023
FTTH Project between Pittsylvania County, River Street Networks & Pittsylvania County Schools
Project Status
â–ªMaterial orders are in place, and some shipments have been received. We
currently have over (400) miles of cable on the yard and over (2) dozen PON
cabinets. In addition, (200) pedestals are arriving on Pitts yard tomorrow for
Michels and Quanta to get started within Sandy Level and Renan, respectively.
Cable and pedestal lead times are very fluid, and materials are on order for all
areas of this project.
â–ªCurrently, the plan is for Michels to build the west side of Pitts, starting in Sandy
Level, then moving south to Strawberry, Brosville, and coming back north to build
Lakeside & Brightsville. Concurrently, Quanta will build the east side of Pitts,
starting at Renan and then moving south into Java, Chestnut, Ringgold, and then
back north to finish Hurt & Gretna.
Pittsylvania PMTC
Serving Area Status Timeline
Brightsville Designed And Awaiting Field
Staking
Q3 2023 Field Staking / Early 2024 Construction Start
At Earliest
Gretna Designed and Awaiting Field
Staking
Q3 2023 Field Staking / Q1 2024 Construction Start
At Earliest
Hurt Designed And Awaiting Field
Staking
Q3 2023 Field Staking / Q1 2024 Construction Start
At Earliest
Lakeside Field Staking 100% Completed,
Construction Contract with Michels
Executed
Construction Starts Concurrently with Sandy Level
Construction Completion Q2-Q3 2023
Renan Field Staking 100% Completed,
Construction Contract with Quanta
Execution Imminent
Construction Start Date TBD Pending Contractor
Addendum Approval but approx. 1/23/23, Equipment
Amounts TBD but (4) Plows & (4) Drills Committed to
by Quanta
Sandy Level Field Staking 100% Completed,
Construction Contract with Michels
Executed
Construction Start Date 1/16/23 Starting Drills in
Round Pond Church Area; Michels starting with (2)
Drills & (2) Plows with more to follow if needed.
Pittsylvania South
Serving Area Status Timeline
Brosville Land Surveyed and Certified,
Awaiting Lease Agreement Execution
Field Staking to start Q2 2023, Construction Start Date
(Michels) Dependent on Materials, Q4 2023-Q1 2024
Java Land Surveyed and Certified,
Awaiting Lease Agreement
Execution, Field Staking 40%
Completed
Construction Start Date (Quanta) Dependent on
Materials, Q3 2023
Ringgold Land Surveyed and Certified,
Awaiting Lease Agreement Execution
Field Staking to start Q2 2023, Construction Start Date
(Quanta) Dependent on Materials, Q4 2023-Q1 2024
Strawberry Land Surveyed and Certified,
Awaiting Lease Agreement
Execution,Field Staking 30%
Completed
Construction Start Date (Michels) Dependent on
Materials, Q3 2023
Chestnut Land Negotiations On Going, Site
May Change, Design & Field Staking
Pending
Construction Start Date (Quanta) Dependent on
Materials, Q4 2023 -Q1 2024
Project
Areas
Pictures of the Drop Yard
PON Cabinets
Handholes & Post