Broadband BOS Presentation 1-17-2023Broadband Update 1/17/2023 FTTH Project between Pittsylvania County, River Street Networks & Pittsylvania County Schools Project Status â–ªMaterial orders are in place, and some shipments have been received. We currently have over (400) miles of cable on the yard and over (2) dozen PON cabinets. In addition, (200) pedestals are arriving on Pitts yard tomorrow for Michels and Quanta to get started within Sandy Level and Renan, respectively. Cable and pedestal lead times are very fluid, and materials are on order for all areas of this project. â–ªCurrently, the plan is for Michels to build the west side of Pitts, starting in Sandy Level, then moving south to Strawberry, Brosville, and coming back north to build Lakeside & Brightsville. Concurrently, Quanta will build the east side of Pitts, starting at Renan and then moving south into Java, Chestnut, Ringgold, and then back north to finish Hurt & Gretna. Pittsylvania PMTC Serving Area Status Timeline Brightsville Designed And Awaiting Field Staking Q3 2023 Field Staking / Early 2024 Construction Start At Earliest Gretna Designed and Awaiting Field Staking Q3 2023 Field Staking / Q1 2024 Construction Start At Earliest Hurt Designed And Awaiting Field Staking Q3 2023 Field Staking / Q1 2024 Construction Start At Earliest Lakeside Field Staking 100% Completed, Construction Contract with Michels Executed Construction Starts Concurrently with Sandy Level Construction Completion Q2-Q3 2023 Renan Field Staking 100% Completed, Construction Contract with Quanta Execution Imminent Construction Start Date TBD Pending Contractor Addendum Approval but approx. 1/23/23, Equipment Amounts TBD but (4) Plows & (4) Drills Committed to by Quanta Sandy Level Field Staking 100% Completed, Construction Contract with Michels Executed Construction Start Date 1/16/23 Starting Drills in Round Pond Church Area; Michels starting with (2) Drills & (2) Plows with more to follow if needed. Pittsylvania South Serving Area Status Timeline Brosville Land Surveyed and Certified, Awaiting Lease Agreement Execution Field Staking to start Q2 2023, Construction Start Date (Michels) Dependent on Materials, Q4 2023-Q1 2024 Java Land Surveyed and Certified, Awaiting Lease Agreement Execution, Field Staking 40% Completed Construction Start Date (Quanta) Dependent on Materials, Q3 2023 Ringgold Land Surveyed and Certified, Awaiting Lease Agreement Execution Field Staking to start Q2 2023, Construction Start Date (Quanta) Dependent on Materials, Q4 2023-Q1 2024 Strawberry Land Surveyed and Certified, Awaiting Lease Agreement Execution,Field Staking 30% Completed Construction Start Date (Michels) Dependent on Materials, Q3 2023 Chestnut Land Negotiations On Going, Site May Change, Design & Field Staking Pending Construction Start Date (Quanta) Dependent on Materials, Q4 2023 -Q1 2024 Project Areas Pictures of the Drop Yard PON Cabinets Handholes & Post Thank you.