Solid Waste Sites Update_111522Convenience Centers
Improvements Update
November 15, 2022
Our engineering consultant has prepared preliminary
improvement plans for three of our existing facilities:
•Mount Hermon (3575 Franklin Turnpike, Danville)
•Motley (1130 Highwayview Road, Hurt)
•Berry Hill (110 Target Drive, Danville)
Convenience Centers Improvements Update
Convenience Centers Improvements Update
Mount Hermon
Draft Expansion
-Adds space for two
new compactors and
two recycling or roll-off
boxes.
Mount Hermon Draft Expansion
Convenience Centers Improvements Update
Mount Hermon -Engineer’s Preliminary Cost Estimate
Paving, Concrete & Traffic Control ----$190,100
Waste Compactor / Containers --------$81,000
Electrical ------------------------------------$42,100
Grading & Erosion Control --------------$26,000
Fencing --------------------------------------$37,500
Contingency & Miscellaneous ----------$92,350 (30%)
Engineering ---------------------------------$41,600
TOTAL-------------$510,650
Motley
Draft Expansion
•Pave existing gravel areas
•Provide new compactor
•Provide payment markings
for better traffic flow
•Additional lighting for
safety & security
•Fence repairs
Motley Site
Convenience Centers Improvements Update
Motley-Engineer’s Preliminary Cost Estimate
Paving, Concrete & Traffic Control ----$135,000
Waste Compactor / Containers --------$72,900
Electrical & Lighting-----------------------$21,100
Fencing --------------------------------------$7,600
Contingency & Miscellaneous ----------$49,110 (30%)
Engineering ---------------------------------$44,250
TOTAL-------------$329,960
Berry Hill
Expansion
Convenience Centers Improvements Update
Berry Hill-Engineer’s Preliminary Cost Estimate
Site Preparation ---------------------------$47,700
Paving, Concrete & Traffic Control ----$98,900
Fencing --------------------------------------$53,300
Site Landscaping & Restoration --------$10,500
Waste Containers --------------------------$8,100
Contingency & Miscellaneous ----------$63,120 (30%)
Engineering ---------------------------------$33,800
TOTAL-------------$315,420
Convenience Centers Improvements Update
Funding Available
There is currently $538,153.88 remaining in our compactor
sites improvement account.
Once the Meadow Ridge Court site is complete, there may
be some leftover funding from the new sites account that
could be reappropriated for these improvements.
Convenience Centers Improvements Update
Prioritization / Recommendation
Due to limited funding, we need to prioritize which site to
move forward on.
Due to the amount of tonnage received at Mt. Hermon,
staff recommends moving forward with that project, with
the others to follow as funding allows.