Loading...
RiverStreet Pittsylvania Co PresentationROBERT TAYLOR –DIRECTOR OF BUSINESS DEVELOPMENT & GOVERNMENT RELATIONS PITTSYLVANIA COUNTY FTTH UPDATE –SEPTEMBER 2022 PITTSYLVANIA COUNTY FTTH UPDATE STEPS IN PITTSYLVANIA COUNTY FTTH BROADBAND PROJECT -The project design has the County broken into eight areas. -Each area requires a site acquisition or lease of property in a centralized location for placement of FTTH equipment. -This includes surveying, zoning applications, site preparation, etc. -During the design phase, -RSN determines pedestal locations, fiber sizing by number of homes and cost efficiency while future proofing our network for the growth of Pittsylvania County. -After the design Phase -RSN orders the necessary material and equipment to meet the design criteria for the FTTH construction. -RSN has acquired a material yard site for storing the construction material. -The material yard requires surveying, site preparation, and obtaining equipment for material handling. -After field surveying are completed the drafting of each area is required to provide installation instructions to the construction crews. -From these design documents the Department of Transportation permits are compiled and submitted for approval by the DOT for projected fiber placement. Pittsylvania County Office Locations •Pittsylvania Peoples •Renan CO (RENF) •Lakeside CO (LKSF) •Gretna CO (GRTF) •Hurt CO (HRTF) •Sandy Level CO (SLVF) •Pittsylvania South •Ringgold CO (RNGO) •Java CO (JAVA) •Strawberry CO (STBR) •Brosville CO (BROS) Renan CO (RENF) Design Progress: 100% Staking Progress: 100% Project Status: Drafting/Permitting Office Location: 181 Straightstone Rd Lakeside CO (LKSF) Design Progress: 100% Staking Progress: 100% Project Status: Final Review and Drafting Office Location: 3650 Smith Mt Rd Gretna CO (GRTF) Design Progress: 25% Staking Progress: TBD Project Status: Design in Progress Office Location: 213 Henry St Hurt CO (HRTF) Design Progress: TBD Staking Progress: TBD Project Status: Design in Progress Office Location: 221 School Rd Sandy Level CO (SLVF) Design Progress: 100% Staking Progress: 90% Project Status: Field Staking & Final Review Office Location: 10941 W Gretna Rd Ringgold CO (RNGO) Design Progress: TBD Staking Progress: TBD Project Status: Site Acquisition/Leasing Office Location: 3880 Tom Fork Rd (Ringgold Vol. Fire Dept) Java CO (JAVA) Design Progress: TBD Staking Progress: TBD Project Status: Site Acquisition/Leasing Office Location: 2904 Java Rd (Riceville Fire Dept) Strawberry CO (STBR) Design Progress: 50% Staking Progress: TBD Project Status: Design in Progress Office Location: 2802 Strawberry Rd (Possumhaw Farm, LLC) Brosville CO (BROS) Design Progress: TBD Staking Progress: TBD Project Status: Site Acquisition/Leasing Office Location: 195 Bulldog Ln (Brosville Elementary) CONSTRUCTION STEPS & TIMELINE FOR THE PITTSYLVANIA COUNTY FTTH BROADBAND PROJECT -DOT encroachment permits to be ready for submission within 4 weeks for 2 of the 8 areas -Approval should be in hand late Nov. –first of Dec. -Construction start first quarter 23’, if not before year end -Main Contractor(s) are working to complete their current routes by end of year -If cable shipments are delayed, we’ll begin placing conduit and blow cable in later -Complete site acquisitions 2nd quarter 23’ -Materials -Cable shipments should start arriving to yard mid December -We have/are redirecting existing cable orders to Pitts yard -+-450 peds will be moved from an existing projects to Pitts yard -Additional orders to yard first of 2nd quarter -Some minor materials have shipped and additional orders to follow as project continues -PON cabinets should be arriving end of 1st quarter COMMUNICATIONS OF THE PITTSYLVANIA COUNTY FTTH BROADBAND PROJECT -First Tuesday of each month WP PDC and RSN will be holding a project update call attended by; -WP PDC Executive Director -WP PDC Grant Administrator -RSN’s Project Coordinator -RSN’s Project Manager -Engineering Firm’s Project Manager -Project Engineer -County Representative -When needed additional members of the RSN team will participate; -RSN Financial Manager, -RSN Marketing Manager, -RSN Operations Manager -Quarterly a member of the RSN Business Development team or higher will present project QUESTIONS THANK YOU!